Zhangqiu, Jinan, Shandong, China Sales 0531-83738299

SC200/200 vs SC100/100: which hoist for 40 floors

2026-11-16 09:00:00 Technical Q&A

Both models reach 40 floors. SC100/100 lifts 2 × 1,000 kg to 150 m; SC200/200 lifts 2 × 2,000 kg to 200 m. On a 130 m building neither is out of its depth, so the choice is decided by three things that have nothing to do with the headline load.

1. Foundation load

SC100/100 roughly halves the load the base has to carry, because the cage, the mast and the drive package are all lighter. On a podium slab or a basement roof that has already been designed, this is often the deciding factor — reinforcing a slab after the fact costs more than the difference between the two hoists.

SC200/200 needs a purpose-built base, typically a 5.6 × 3.8 m raft with anchor bolts cast in. If the site cannot give you that footprint at ground level, a single-cage SC100 is the cheaper answer than a redesign.

2. Power supply

ItemSC100/100SC200/200
Drive motors per cage2 × 11 kW3 × 11 kW
Connected load, two cages44 kW66 kW
Starting currenthigh, direct-on-linehigh, direct-on-line
VFD optionSC100/100 VFDSC200/200 VFD

On sites where the tower crane and the hoist share one generator, 66 kW of connected load plus a direct-on-line start is often the real constraint. The VFD version does not reduce connected load but it does cut the start current to near rated, which is what trips breakers.

3. Cyclic demand at peak

Count the trips per hour during the busiest phase — usually fit-out, when trades and finishes move together. A 2,000 kg cage carries roughly twice the tiles, boards or blocks per trip, but it does not travel faster: both run at 34 m/min. On a 130 m building that is about 2 minutes per round trip excluding loading, so the gain comes from load per trip, not cycle time.

Where the peak is people rather than material — a residential tower handing over floors — the number of cages matters more than their capacity. Two SC100/100 cages moving 12 persons each beat one large cage on waiting time.

Where SC100/100 wins

  • The building tops out below about 30 floors and the peak load is finishes, not structure.
  • The foundation is an existing slab with a load limit already calculated.
  • Site power is capped and no generator upgrade is planned.
  • The hoist is bought for resale or rental, where a lighter unit is easier to place.

Where SC200/200 is the safer order

  • Concrete and precast panels are lifted with the hoist, not only with the crane.
  • The tower exceeds 150 m and the mast has to be extended later.
  • The contractor runs a mixed fleet and wants one spare-parts list for every hoist.

Frequently asked

Can I start with SC100/100 and upgrade later? The mast geometry is the same 650 × 650, but the cage, drive and safety device are not interchangeable. Treat it as a separate machine.

Does SC200/200 need a bigger tie-in? Yes — tie-in loads scale with cage mass and mast height, so the wall anchors are heavier and more closely spaced.

Which is cheaper to ship? SC100/100 fits more mast sections per 40HQ because the drive package is lighter; the difference is roughly one container per two machines at 150 m.

Related: SC100/100 dual-cage hoist · SC200/200 VFD · 650 × 650 mast section

← Back to list Request a quote
How to read a construction hoist load chart

Send the site data, get a configuration and a price

Building height, required payload and power supply are enough for us to come back with a model, a drawing and a delivered price within one working day.

15688868277